Under Construction
UAE > Dubai > Jumeirah Village Circle (JVC) > District 10 > Stonehenge Residences
| Description | Milestone Event | (%) Value |
|---|---|---|
| Down Payment | Immediate | 5% |
| 1st Installment | Within Months of Sale Date | 15% |
| 2nd Installment | Within Months of Sale Date | 10% |
| 3rd Installment | Within 8 Months of Sale Date | 10% |
| 4th Installment | Within 13 Months of Sale Date | 10% |
| 5th Installment | Within 16 Months of Sale Date | 10% |
| Payment At Handover | On Completion | 40% |
Title :
Stonehenge Residences
Type :
Free Hold
Project Number :
N/A
Completion Status :
Under Construction
Life Cycle :
N/A
Master Development :
District 10
Developer :
Plot Number :
6816114(JVC10AAMRM003)
Project Configuration :
3B+G+10+R
Number Of Units :
156
Number Of Sold Units :
N/A
Number Of Remaining Units :
N/A
Number Of Floor :
10
Plot Area :
N/A
Built Up Area :
10,963 Square Feet
Status Percentage :
93
Launch Date :
01-Feb-2023
Registration Date :
17-May-2023
Construction Started Date :
01-Feb-2023
Anticipated Completion Date :
31-Mar-2025
Cost Consultants :
N/A
Piling Contractors :
N/A
Handover Date :
01-Jan-2025
Main Contractors :
Aroma International Building Contractors
Sub Contractors :
N/A
Architects :
N/A
MEP Contractors :
N/A
Project Managers :
N/A