UAE > Dubai > Damac Hills > Golf Gate > Golf Gate 2
Completion Status
Payment Plan
Handover
| Description | Milestone Event | (%) Value |
|---|---|---|
| Down Payment | Immediate | 20% |
| 1st Installment | Within 7 Months of Sale Date (1st to 5th Installment) | 5% |
| 2nd Installment | Within 15 Months of Sale Date (6th Installment) | 10% |
| 3rd Installment | Within 29 Months of Sale Date (7th to 12th Installment) | 6% |
| 4th Installment | Within 44 Months of Sale Date (13th Installment) | 12% |
| 5th Installment | Within 64 Months of Sale Date (14th to 18th Installment) | 5% |
| 6th Installment | Within 85 Months of Sale Date (19th Installment) | 12% |
| Payment At Handover | On Completion | 30% |
| 1st Installment | Within 7 Months of Completion (1st to 5th Installment) | 5% |
| 2nd Installment | Within 15 Months of Completion (6th Installment) | 10% |
| 3rd Installment | Within 29 Months of Completion (7th to 12th Installment) | 6% |
| 4th Installment | Within 44 Months of Completion (13th Installment) | 12% |
Title :
Golf Gate 2
Type :
Free Hold
Project Number :
2698
Completion Status :
Under Construction
Life Cycle :
Developing
Master Development :
Golf Gate
Developer :
Plot Number :
6767876
Project Configuration :
G+2P+27
Number Of Units :
464
Number Of Floor :
30
Plot Area :
253,233 Square Feet
Built Up Area :
848,121 Square Feet
Construction Status :
43.25
Launch Date :
01-Jun-2023
Registration Date :
20-Jun-2023
Construction Started Date :
03-Aug-2023
Anticipated Completion Date :
01-Jan-0001
Cost Consultants :
N/A
Piling Contractors :
N/A
Handover Date :
N/A
Main Contractors :
N/A
Sub Contractors :
N/A
Architects :
N/A
MEP Contractors :
N/A
Project Managers :
N/A
Key Features of Golf Gate: