Under Construction
UAE > Dubai > Jumeirah Village Circle (JVC) > District 15 > Binghatti Onyx
| Description | Milestone Event | (%) Value |
|---|---|---|
| Down Payment | Immediate | 50% |
| 1st Installment | Within Months of Sale Date | 20% |
| Payment At Handover | On Completion | 30% |
| Description | Milestone Event | (%) Value |
|---|---|---|
| Down Payment | Immediate | 0% |
| 1st Installment | Within Months of Sale Date | 50% |
| Payment At Handover | On Completion | 50% |
| Description | Milestone Event | (%) Value |
|---|---|---|
| Down Payment | Immediate | 0% |
| 1st Installment | Within Months of Sale Date | 70% |
| Payment At Handover | On Completion | 30% |
Title :
Binghatti Onyx
Type :
Free Hold
Project Number :
N/A
Completion Status :
Completed/Ready
Life Cycle :
N/A
Master Development :
District 15
Developer :
Plot Number :
JVC15DHRA100(6817340)
Project Configuration :
B+G+4P+ 36+R
Number Of Units :
507
Number Of Sold Units :
N/A
Number Of Remaining Units :
N/A
Number Of Floor :
41
Plot Area :
50,622 Square Feet
Built Up Area :
46,745 Square Feet
Status Percentage :
100
Launch Date :
01-Feb-2023
Registration Date :
12-Apr-2023
Construction Started Date :
23-Mar-2023
Anticipated Completion Date :
10-Jan-2024
Cost Consultants :
N/A
Piling Contractors :
N/A
Handover Date :
01-Oct-2024
Main Contractors :
Granada Europe Engineering Contracting Company
Sub Contractors :
N/A
Architects :
N/A
MEP Contractors :
N/A
Project Managers :
N/A