Under Construction
UAE > Dubai > Motor City > Beverly Grande
Description | Milestone Event | (%) Value |
---|---|---|
Down Payment | Immediate | 20% |
1st Installment | Within 2 Months of Sale Date | 10% |
2nd Installment | Within Months of Sale Date | 10% |
3rd Installment | Within Months of Sale Date | 10% |
4th Installment | Within Months of Sale Date | 10% |
Payment At Handover | On Completion | 40% |
Title :
Beverly Grande
Type :
Free Hold
Project Number :
N/A
Completion Status :
Planned
Life Cycle :
N/A
Master Development :
Motor City
Developer :
Plot Number :
N/A
Project Configuration :
G+10
Number Of Units :
296
Number Of Sold Units :
N/A
Number Of Remaining Units :
N/A
Number Of Floor :
11
Plot Area :
N/A
Built Up Area :
21,886 Square Feet
Status Percentage :
N/A
Launch Date :
N/A
Registration Date :
28-May-2025
Construction Started Date :
15-Aug-2025
Anticipated Completion Date :
31-Dec-2027
Cost Consultants :
N/A
Piling Contractors :
N/A
Handover Date :
01-Apr-2027
Main Contractors :
N/A
Sub Contractors :
N/A
Architects :
N/A
MEP Contractors :
N/A
Project Managers :
N/A